Cost Contingency estimation: a new method for Quantitative Risk Analysis applied to a real construction project

  1. CURTO LORENZO, DAVID 1
  2. POZA GARCIA, DAVID JESUS 1
  3. VILLAFAÑEZ CARDEÑOSO, FELIX ANTONIO 1
  4. ACEBES SENOVILLA, FERNANDO 1
  1. 1 Universidad de Valladolid (España)
Zeitschrift:
DYNA

ISSN: 1989-1490

Datum der Publikation: 2024

Ausgabe: 99

Nummer: 1

Seiten: 106-112

Art: Artikel

DOI: 10.6036/10815 GOOGLE SCHOLAR lock_openOpen Access editor

Andere Publikationen in: DYNA

Zusammenfassung

he main objective of this work is to propose a method based on Monte Carlo simulation (MCS) to estimate the allocation of project cost contingency reserves in the planning phase, incorporating the different types of uncertainty described in the literature, associating them to each of the risks identified in the project. The method was applied to validate our proposal on an actual construction project carried out by the University of Valladolid (Spain).Applying the proposed method has allowed us to obtain a more accurate estimate of cost contingencies than the method traditionally used by the company, which consisted of reserving a fixed and arbitrary percentage of the total project execution budget.